Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

South Korea (AS.KR)

Planning/Scheduling Engineer, SK Engineering & Construction, HANAM Power Project, RP Energy

START Date: 
June, 2011
END Date: 
June, 2013

·         Project planning, scheduling and monitoring involved in EPC projects (Oil & Gas / Power Plants).

·         Review of ITB documents and project details.

·         Detailed project review for preparation of proposal schedules.

Experience Hours (Planning & Scheduling): 
4800

Planning & Cost Engineer, Samsung Heavy Industries Co. Ltd., Takula Gas Processing Platform Project

START Date: 
February, 2007
END Date: 
December, 2009

FLEXLNG LNG Producer 1 Project – Norway ($550M - 1.7MTPA)

  • Participated and won project bidding for a 1.7MTPA FLNG Project.
  • Prepared project budget and cost forecasting, monthly cash flow forecast and cost report, invoice and payment request review and evaluation report.
  • Analysed project schedule and progress; compared schedule against cash flow.

Takula Gas Processing Platform Project – Angola ($242M - 250MMSCFPD)

Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Cost Management): 
6000
Experience Hours (Forensic Analysis): 
6000

Planning & Cost Engineer, Pacific Drilling Construction Ltd., Pacific Bora Ultra Deepwater Drillship Project

START Date: 
March, 2010
END Date: 
March, 2011

Pacific Bora Ultra Deepwater Drillship Project – South Korea ($850M - 12,000ft. water deep capability)

  • Prepared construction schedule and post-delivery modifications schedule of the new built drillship.
  • Managed the controls of project budget and invoice review of the drillship rig readiness and upgrade project.
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
2000

Project Control MAnager, TOTAL E&P, Timimoun LNG Field Development Project

START Date: 
May, 2014
END Date: 
January, 2016

·         Form, Train and Manage Project Team

·         Define and manage stakeholders

·         Develop project procedures, example: PMP

·         Develop and maintain level 3 Time Schedule

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
40000
Experience Hours (Forensic Analysis): 
35000

Vikas Ranjan

First Name: 
Vikas
Last Name: 
Ranjan

A Mechanical Engineer working in the field of Project Management since 2007. I have worked as a planning and project control Engineer in the oil and Gas industry(upstream).

Professional Since: 
Feb-2006 (18.5 yrs experience)
Oldest experience: 
Feb 2006 (18.5 yrs experience)
Years Experience: 
8

Assistant Manager - Planning Engineer, Samsung Heavy Industries, Offshore Platform

START Date: 
July, 2015

Planning Engineer at samsung Heavy Industries,Geoje, South Korea. Roles includes Scheduling,control and Reporting.

Experience Hours (Planning & Scheduling): 
1600

Assistant Manager - Planning Engineer, Samsung Heavy Industries, Offshore Platform

START Date: 
July, 2015

Planning Engineer at samsung Heavy Industries,Geoje, South Korea. Roles includes Scheduling,control and Reporting.

Experience Hours (Planning & Scheduling): 
1600

Yeongjoon Pyeon

First Name: 
Yeongjoon
Last Name: 
Pyeon

Head of Overseas Legal Team

Contract review and negotiation

Educating staffs in Contract Management

supporting site in solvong contractual and claim issues

Professional Since: 
Nov-1997 (26.7 yrs experience)
Oldest experience: 
Mar 1983 (41.4 yrs experience, WARNING: 14.7 years variance with Professional Since)
Years Experience: 
46

senior planning engineer, GS E&C , JI-0563 Ruwais 4th NGL Train Project

START Date: 
October, 2009
END Date: 
August, 2010

v  Major Responsibilities include Planning and Scheduling of Ruwais NGL Train 4 Project. 

v  Preparation of Level I to Level III EPC Schedule of the Project.

v  Preparation of Risk Analysis Register and Mitigation plan for critical activities.

v  Preparation and reporting of EPC Progress Summary and Updation.

Preparation and Progress Payment Invoicing based on Work completion at WBS Level

Experience Hours (Planning & Scheduling): 
1600

senior planning engineer, GS E&C , JI-0563 Ruwais 4th NGL Train Project

START Date: 
October, 2009
END Date: 
August, 2010

v  Major Responsibilities include Planning and Scheduling of Ruwais NGL Train 4 Project. 

v  Preparation of Level I to Level III EPC Schedule of the Project.

v  Preparation of Risk Analysis Register and Mitigation plan for critical activities.

v  Preparation and reporting of EPC Progress Summary and Updation.

Preparation and Progress Payment Invoicing based on Work completion at WBS Level

Experience Hours (Planning & Scheduling): 
1600

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content