Shaybah Central Processing Facilities – Gas Oil Separator

Planning & Schedule & Cost Control Leader, Ltd, Nesma & Partners Contracting Co., Shaybah Central Processing Facilities – Gas Oil Separator

START Date: 
August, 2007
END Date: 
February, 2008
  • Supervise the planning engineers to develop the Work measurement System by detailing the contract scope.
  • Arrange the projects Manpower Histogram based of the company productivity Rate.
  • Supervise the planning engineers to develop the Level IV Schedule.
  • Follow up the projects Progress & Regular Visit for all projects. 
  • Preparing the yearly budget of the company.
  • Preparing the combined progress Report.
  • Preparing the projects budget.
  • Preparing the executive Reports (Monthly Cost & and the forecast cost at completion)