Replacement of Machinery Foundation in Power Plants and Flare

CIVIL / PLANNING ENGINEER, ARAMCO-KJO THRU: BHSC, Replacement of Pipe Sleepers in GOSP, Replacement of Oil Tank Foundation and Dikes, Replacement of Machinery Foundation in Power Plants and Flare , Offshore Maintenance Works in Oil Rig / Platform, Minor C

START Date: 
July, 2006
END Date: 
August, 2008
  • Prepare project master schedule and project detailed schedules.
  • Monitoring and Controlling of the integrated schedule of all project activities including Civil, Mechanical and Electrical during the construction phase.
  • Prepare reports on Baseline vs Current Schedules plus analysis on forecast for weekly progress report to the top project management team.
  • Interface with Engineering, Construction and Commissioning activities to align activities according to plan
  • Preparation of float and critical path analysis
  • Issue Project Weekly/Monthly