I was Lead planning engineer for Shanahan Engineering working on the short term commissioning programme of block 2 of the 2.2gw CCGT PP-12 power station 140km west of Riyadh, total make up across the plant of 8 Gas Turbines, 8 HRSG’s & 2 Steam Turbine’s.