Power Transmission Lines

Planner, b, Power Transmission Lines

START Date: 
November, 2011
END Date: 
May, 2014

Planner for $1.2B transmission line project in Alberta.  Responsibiliities included progress update, subcontract plan review and implementation. Development of project WBS and reporting methods and tools.

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
1000

Senior Programmer, United Group Limited, Power Transmission Lines

START Date: 
May, 2010

Prepare detailed construction programme, carry out regular updates and forecast look ahead programmes, prepare extension of time claims etc