Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Planner, b, Power Transmission Lines

START Date: 
November, 2011
END Date: 
May, 2014

Planner for $1.2B transmission line project in Alberta.  Responsibiliities included progress update, subcontract plan review and implementation. Development of project WBS and reporting methods and tools.

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
1000