Open-Cycle Gas Turbines (5 off) Power Station Build

Senior Planner, Eskom CED, Open-Cycle Gas Turbines (5 off) Power Station Build

START Date: 
June, 2008
END Date: 
November, 2008

• For J&M Project Management Services, performing a site-based planning function for the successful completion of the ‘ESKOM Gas1’ Project (5 new Open-Cycle 150MW Gas Turbine Generators) at Ankerlig Power Station in the Western Cape of South Africa.
• Creating detailed schedules for various aspects of the above project i.e.

Experience Hours (Planning & Scheduling): 
1000