Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

National Grid ISS

PLANNING ENGINEER, J Murphy & Sons, National Grid ISS

START Date: 
February, 2013
END Date: 
April, 2013

ISS project for national Grid involves the construction of Electrified Security Fencing and Security measures within Electricity Substations and Gas A.G.I.’s on a design and build basis. This is a framework contract lasting for 3 years with a turnover in excess of £40 Million Per Annum. Responsible for all planning duties for 3 designs & 3 construction sites in and around the South West. Based on one of the live construction sites at least 3 days a week.

 

Experience Hours (Planning & Scheduling): 
400
Experience Hours (Cost Management): 
200

Market Place

No results found... (try selecting a different content filter)

Syndicate content