Manger Planning, Essar Offshore and Subsea Ltd., Offshore Platforms,Pipelaying,Modifications

START Date: 
May, 2010
END Date: 
January, 2013
• Preparation of official EPCI planning package for offshore platforms projects for ONGC. • Schedule Analysis/Updation/Monitoring. • Variance Analysis , Delay Analysis • Carefully laying out onshore and offshore schedule for entire project. • Preparation of DCI/MCI for Engineering. • Schedules using Primavera to plan and monitor all the offshore activities for projects. • Fabrication planning for offshore Jackets/Decks/Piles/Conductors. • Preparation of Daily / Weekly /monthly progress report. • Preparation of internal and external presentations. • Coordination with overse
Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
5000