Project Controls Engineer, Banu Mukhtar Contracting (Pvt.) Limited, Buildings & Infrastructures, COMMERCIAL & RESIDENTIAL BUILDINGS, Mixed use development, Multiple Projects ; Oil & Gas

START Date: 
September, 2009
END Date: 
April, 2012
  • Construction Planning and Scheduling (Resource & Cost Loaded Master Schedules) using PRIMAVERA 6 & MS PROJECT 2010
  • Identification, monitoring& streamlining of critical paths running through the Project Schedule.
  • Using Earned Value Calculations to monitor project status.
  • Analysing Trends and development of early warning system.
  • Developing Budgets that lead to the establishment of a cost/schedule baseline.
  • Resource and cost management using MS PROJECT & PRIMAVERA.
  • Contractual correspondence

Senior Planning Engineer, Drake & Scull International, Mixed use development

START Date: 
July, 2010

·       Development of Pre- Contract and Post- Contract Program Schedules, Work Breakdown Structures, Project Execution Plan and Method Statements

·       Coordinate with Project Team, Commercial dept., Engineering dept., Procurement dept., to prepare PM Budget, Project Cash Flow and Histograms, Information Required Schedule, Engineering Schedule, Material Submissions and Procurement Schedule