Mitsubishi Electric Europe B.V - Networks Islington Substation Project & Loondon Underground Infrastructural Renewal Project

Project Control Consultant , GMH Planning Limited , Mitsubishi Electric Europe B.V - Networks Islington Substation Project & Loondon Underground Infrastructural Renewal Project

START Date: 
January, 2013
END Date: 
July, 2013

Responsible for developing a detailed, logic linked, resourced and cost loaded programme that aligns with the submitted Activity Schedule that conforms to the minimum level of detail required within the WBS structure attached. Ensured the programme demonstrates compliance with the sectional completion dates & Contractors time risk allowances.

&

Experience Hours (Planning & Scheduling): 
950
Experience Hours (Cost Management): 
950