Meydan Racecourse

Planning and Scheduling Engineer., Saudi Binladin Group-PBAD, Arabtec Construction Dubai LLC., King Abdullah Financial District-Riyadh -KSA, Meydan Racecourse, SkyGarden Tower, Jumeirah Beach Residence

START Date: 
August, 2004
END Date: 
May, 2012

Duties and responsibilities:

  • Prepare all planning and programming works such as baseline schedule, cost loading, manpower and equipment resource loading, recovery programme, monthly update, weekly look ahead schedule.

Forensic Scheduling Team Lead, Arabtec Construction, Meydan Racecourse

START Date: 
February, 2010
END Date: 
April, 2010

Lead forensic team in collecting data to generate an As-Planned vs. As-Built analysis of delays to the Meydan Racecourse in Dubai.  Researched contemporaneous project documents, converted spreadsheet logs into database, cleaned up data to allow full searches, reviewed RFIs, change orders, baseline and update schedules, and time impact analyses.  Developed position on impact events, prepared presentation documents.

Experience Hours (Planning & Scheduling): 
150
Experience Hours (Cost Management): 
150
Experience Hours (Forensic Analysis): 
100