Mbalam-Nabela Iron Ore Project

Principle Projects Planner, Sundance Resources, Mbalam-Nabela Iron Ore Project

START Date: 
June, 2010
END Date: 
October, 2014

Mbalam-Nabela Iron Ore ProjectUS$6 Billion 35 Million tonnes per annum Iron Ore Project in Cameroon and Congo (West Africa) consisting of  600km Rail, Iron Ore process Plant, Port Material Handling and Ship loading facility, Airport & Accommodation facilities

Principal Projects Planner (7 months full time, then consulting role as required)6/2010to 10/2014

Experience Hours (Planning & Scheduling): 
5900
Experience Hours (Cost Management): 
1650
Experience Hours (Forensic Analysis): 
500