Leman Uptime Power Generation Project

Senior Planning Engineer, AMEC, Leman Uptime Power Generation Project

START Date: 
January, 2010
END Date: 
January, 2011

Senior Planning Engineer Leman Uptime Power Generation Project, largest Brownfield Modification scope of work in the history of the Southern North Sea – Client SHELL. Change out of antiquated/damaged Ruston Generators for three new Pon Power (Caterpillar) Gas Turbine Generators weighing 16.5 tonnes in total. Upgrade of Control and Safety System within the live platform Local Equipment Room.  Responsible for the creation, management, manipulation of Level 4 Construction/Pre-Commissioning/Commissioning Plan consisting of 2500 activities.