KKNPP

Site supervisor, Guru Engineering, 2x1000 mw Nucelar Power Project, KKNPP

START Date: 
August, 2007
END Date: 
August, 2010

Erection of Structural Assy. platforms , hand rails , tank side and top rail & platforms

Insulation of boiler (refractory concrete)

Erection of Underground well Ladder Erection

Firehose location arrangement

Planning Asst., Contract, 2x1000 mw Nucelar Power Project, KKNPP

START Date: 
August, 2010

Daily Contract Management ,Progress monitoring & reporting , Billing Preparation as per SOQR

Experience Hours (Planning & Scheduling): 
19000
Experience Hours (Cost Management): 
19000