Site supervisor, Guru Engineering, 2x1000 mw Nucelar Power Project, KKNPP
START Date:
August, 2007
END Date:
August, 2010 Erection of Structural Assy. platforms , hand rails , tank side and top rail & platforms
Insulation of boiler (refractory concrete)
Erection of Underground well Ladder Erection
Firehose location arrangement
- Company:
- Industry:
- Job Role:
- Project:
- Region: