START Date:
October, 2016
- Responsible for initial preparation, financing, organizing key crew and establishing organization chart. Closely communicated with senior management of National Iranian Oil Company (NIOC), generated the general schedule and programmed for NIOC and SEI and Consortium, and defined specific action plans. In charge of project managers from both sides and issued a detailed project objectives and milestones.
Experience Hours (Planning & Scheduling):
2200
Experience Hours (Cost Management):
900
Experience Hours (Forensic Analysis):
1200