- Preparing the Master Programme of Works for various Projects with the scope in Sewerage, Storm Water, Water Works, Irrigation, Electrical, Telephone, Road Works, Substation, Irrigation Reservoir/Pump Station, other essential utilities, Highways, Parking, Landscaping, Brdiges, and Airport.
- Prepare monthly reports, weekly reports, daily reports and night shift report.
- Update of Over-All Programme of works, 60-days look ahead and 3-weeks look ahead.
- Prepare and submit the project status report, equipment and manpower.
- Prepare and submit updated/re