Devenick

Planner, Technip, Devenick

START Date: 
January, 2011
END Date: 
March, 2011

 

  • Work closely with the Project Team to create Level 3 Tender schedules for various projects and clients, in MS Project 2007.
  • Create various option schedules to cover all client options, and compare schedule impact between the options with the project team.
  • Once awarded, convert the project into P3 and include costs, and track progress.
  • Issue monthly S-curves and histograms to the project team, for inclusion into the monthly report to the client.