Planning Engineer & Cost Control, J Murphy & Sons Limited, CTRL 320 - Thames Tunnels

START Date: 
March, 2001
END Date: 
October, 2005

·         Involved in preparing the project Work Breakdown Structure (WBS)

·         Updated & maintained contract construction programmes

·         Produced & maintained Time Chainage Programmes & Schematic Progress diagrams