Planning Engineer & Cost Control, J Murphy & Sons Limited, CTRL 320 - Thames Tunnels
START Date:
March, 2001
END Date:
October, 2005 · Involved in preparing the project Work Breakdown Structure (WBS)
· Updated & maintained contract construction programmes
· Produced & maintained Time Chainage Programmes & Schematic Progress diagrams
· Cost control (Budget, Actual Cost, Earned Value)Using ARISTOTELES (Module Kubus)