Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Project Planner/ Scheduler

Project Planner/ Scheduler, MEG Energy, CPF Construction

START Date: 
February, 2012
END Date: 
February, 2015

Maintenance, Shutdown & Turnaround Scheduler - Current

 

Project planner/ scheduler (Central Plant Facility) - Feb 2012 to Feb 2015

- EP, FC interface planning to identify critical and key drivers to 1st steam date - Level 2 development

- Level 3 schedule development for FC portion

 

Project planner/ scheduler (Pipeline)

- Regulatory, EP, FC interface planning to identify critical and key drivers to in service date - Level 2 development

- Level 3 schedule development for Regulatory, P, FC portion

Project Planner/ Scheduler, MEG Energy, CPF Construction

START Date: 
February, 2012
END Date: 
February, 2015

Maintenance, Shutdown & Turnaround Scheduler - Current

 

Project planner/ scheduler (Central Plant Facility) - Feb 2012 to Feb 2015

- EP, FC interface planning to identify critical and key drivers to 1st steam date - Level 2 development

- Level 3 schedule development for FC portion

 

Project planner/ scheduler (Pipeline)

- Regulatory, EP, FC interface planning to identify critical and key drivers to in service date - Level 2 development

- Level 3 schedule development for Regulatory, P, FC portion

Project Planner/ Scheduler, MEG Energy, CPF Construction

START Date: 
February, 2012
END Date: 
February, 2015

Maintenance, Shutdown & Turnaround Scheduler - Current

 

Project planner/ scheduler (Central Plant Facility) - Feb 2012 to Feb 2015

- EP, FC interface planning to identify critical and key drivers to 1st steam date - Level 2 development

- Level 3 schedule development for FC portion

 

Project planner/ scheduler (Pipeline)

- Regulatory, EP, FC interface planning to identify critical and key drivers to in service date - Level 2 development

- Level 3 schedule development for Regulatory, P, FC portion

Project Planner/ Scheduler, Leighton Contractors Pty Ltd, QUT SciTech

START Date: 
July, 2010

Required to develop and expand on the current project programme whilst scheduling and providing progress reports to both the client and subcontractors.

Project Planner/ Scheduler, Aker Solutions, Kashagan Development Project, Offshore

START Date: 
January, 2009

Company                               : Aker Solutions Contracting AS

Type                                : Heavy Construction – Oil & Gas (EPC Contractor).

Project    &nb

Project Planner/ Scheduler, Vanderlande Industries, Schiphol / Heathrow Airport

START Date: 
June, 2008

- Support the project team and the project manager in particular in planning the project. Schiphol is a customer of Vanderlande.

Project Planner/ Scheduler, Kumba Iron Ore, Sishen South Project

START Date: 
April, 2008

Current Role

Project Planner on a Greenfields Mining Construction Project in South Africa since April 2008. Responsibility Areas:

  • Roads and Infrastructure
  • Water Export Pipeline
  • Railway
  • Operational readiness

All Planning related functions.

Project Planner/ Scheduler, National Grid UK, HV Substations

START Date: 
December, 2005

Current Role

Responsible for developing detailed work breakdown structures within Primavera to ensure the efficient and effective monitoring of multi million pound projects.  These projects encompass the refurbishment or construction of HV substations to facilitate customer connections and greater load on to the National Grid network as demand increases

 

  • Delivery programmes are fully resourced, coded and cost loaded and include end to end detailed engineering design (primary and secondary), procurement, civil works and M&E installation

Market Place

No results found... (try selecting a different content filter)

Syndicate content