Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Project Control Systems Manager

Project Control Systems Manager, SSH International Consultants, Various

START Date: 
May, 2004
END Date: 
February, 2007

·     Developed and updated the WBS, RBS and Master Schedule in Primavera which is used as the basis for resource planning, budgeting, cost control and reporting for all ongoing and prospective design and construction supervision projects

·     Supported multiple construction supervision sites with respect to CCS review and approval, cost and resource loading of activities, and variation claims analysis

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
2000

Market Place

No results found... (try selecting a different content filter)

Syndicate content