Project Control Systems Manager, SSH International Consultants, Various

START Date: 
May, 2004
END Date: 
February, 2007

·     Developed and updated the WBS, RBS and Master Schedule in Primavera which is used as the basis for resource planning, budgeting, cost control and reporting for all ongoing and prospective design and construction supervision projects

·     Supported multiple construction supervision sites with respect to CCS review and approval, cost and resource loading of activities, and variation claims analysis

·     Implemented and maintained the Project Controls System which integrated the Administrative and Operational procedures for 185 employees, including networking, hardware and software integration, set-up, associated training, and maintenance.  Managed the full implementation of a design management software solution that ensured standardization and integrity of information and achieved an 80% paper-less office

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
2000