Project Control Superintendent

Project Control Superintendent, ICA Fluor Daniel, •Minera y Metalúrgica El Boleo, Copper, Cobalt, Zinc Mine, Santa Rosalía, BCS, Mex

START Date: 
August, 2010
END Date: 
February, 2014

EPC Planning and Schedule Lead, EPC Progress tracking and Reporting, Risk Analysis

Experience Hours (Planning & Scheduling): 
7550

Project Control Superintendent, BHP Billiton, Escondida Concentrate Transport

START Date: 
September, 2013
END Date: 
October, 2014

Leading the project control owner team, leading professionals in charge of planning, scheduling, cost control, change manafement, governance an reporting

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
700
Experience Hours (Forensic Analysis): 
700