Planner / Project Manager

Planner / Project Manager, Service Birmingham, PIC Launch

START Date: 
June, 2008
END Date: 
August, 2008

Project Managed relaunch of department under new name and expanded remit.

Existing department was named Business Support Unit and operated as a pool of employees who were placed on assignments to various project and programmes on client sites.  Relaunched department as Professional Internal Consultancy.

Planner / Project Manager, Service Birmingham, PIC Launch

START Date: 
June, 2008
END Date: 
August, 2008

Project Managed relaunch of department under new name and expanded remit.

Existing department was named Business Support Unit and operated as a pool of employees who were placed on assignments to various project and programmes on client sites.  Relaunched department as Professional Internal Consultancy.

Planner / Project Manager, Various, Various

START Date: 
October, 2001
END Date: 
October, 2009

Construction Site Project Management.  On Various New Build , Refurbishment Projects to the value of  £15m.

 

Working within the Commercial , Pharmaceutical , Decent Homes , Residential , Leisure and Civil Engineering Sectors

Planner / Project Manager, Dafora Medias, Various - Civil Engineering

START Date: 
August, 2004

Project Manager for 5 civil buildings in a total amount of 40 mil euros

Planner / Project Manager, Various, Buildings and Infrastructure

START Date: 
August, 1977

Over thirty years experience in senior project and construction management positions in building, infrastructure, power and rail projects.

Planner / Project Manager, MCR, LLC, Various

START Date: 
January, 2006

Mr. Evans was the Project Control Lead/Master Scheduler for the U.S. Transportation Command (TRANSCOM) Defense Personal Property System (DPS) program. He established an ANSI-748 compliant Earned Value Management System (EVMS) for the program and guided the program through a successful Integrated Baseline Review. The EVMS used Microsoft Project 2003, Deltek Cobra 5, and Deltek wInsight 6.4.

Planner / Project Manager, Marconi, Jubilee Line Extension

START Date: 
June, 1999
END Date: 
August, 2000

Controlled simultaneously several projects within the London Underground Jubilee Line Extension Project including installation and inspection of Public Address System equipment, development of a fault analysis/maintenance monitoring and control system and Radio Communications System equipment. 

Compilation of method statements, obtaining of access permissions and work completion certification documents for work in station control rooms, equipment rooms and other non-public areas.

Planner / Project Manager, Gardiner & Theobald, Colosseum, Bucharest

START Date: 
April, 2007
END Date: 
May, 2008

Planner / Project manager for Gardiner and Theobald based in Bucharest, Romania

Planner / Project Manager, McCabe builders uk ltd, Eagle house

START Date: 
June, 2008
END Date: 
February, 2012

Current Role. On a day to day basis I am responsible for the management of the McCabe Eagle House site team together with ensuring correct control of both safety and construction activities of the Eagle House Project are maintained.

My role also includes management of the design team to ensure clients requirements are integrated into the design and ensuring programme , finish and cost controls are adhered to.

i undertake all planning and programming of the project and oversee any consultant design team meetings and subcontractor meetings that are taking place.

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
1000

Market Place