Commissioning Planning Engineer

Commissioning Planning Engineer, TOTAL, Coke & Sulfur Handling Project

START Date: 
September, 2001
END Date: 
October, 2002

Developed a full pre-commissioning and commissioning network down to task and discipline level with coding structure to produce reports by System, Contractor, Discipline and Project Phase.

The project involved the commissioning of a Conveyor System to transport Coke and Sulfur Products from the main Upgrader Complex to shipping jetties.

Commissioning Planning Engineer, Total, Sincor Upgrader Project

START Date: 
August, 2000
END Date: 
September, 2001

Working as part of the Project Management Team developing the Commissioning Programme for the Upgrader Complex which comprised a Desalting and Crude Distillation Unit, Delayed Coking Unit, Sulfur Recovery Unit, Gas Sweetening Plant, Mild Hydrocracker and Hydrogen Manufacturing Unit (project total ~$4.2 billion).

Produced Integrated and summarised programmes to system level from the more detailed programmes of Main Contractors as well as the Operating Group. Preparation of reports and presentations to Commissioning Manager and Partnership Directors.