ANALYST / PLANNING ENGINEER

ANALYST / PLANNING ENGINEER, HASSAN ALLAM SONS (MISR SONS DEVELOPMENT), ERC

START Date: 
June, 2014
  1. Understand work scope, quantity and familiar with logical sequences in terms of engineering, manufacturing and construction disciplines.
  2. Conduct field scoping to clarify scope as required.

ANALYST / PLANNING ENGINEER, AECOM Middle East, Dubai Metro

START Date: 
August, 2008
END Date: 
May, 2011

o    Review the project contract program, resource plans and key performance indicators.

o    Supervise project progress and subcontractor planners.

o    Review and analyze extension of time claim by Subcontractor.

o    Extension of time presentation – Retrospective analysis.

o    Assist Quantum analyst calculating time-related compensation.

ANALYST / PLANNING ENGINEER, M4 Contracting SARL, Radar Buidling at Al Ain International Airport

START Date: 
July, 2015

Airports Projects- Primavera P6, Project Management, Risk Management, Project Planning and Billing

ANALYST / PLANNING ENGINEER, M4 Contracting SARL, Radar Buidling at Al Ain International Airport

START Date: 
July, 2015

Airports Projects- Primavera P6, Project Management, Risk Management, Project Planning and Billing

ANALYST / PLANNING ENGINEER, M4 Contracting SARL, Radar Buidling at Al Ain International Airport

START Date: 
July, 2015

Airports Projects- Primavera P6, Project Management, Risk Management, Project Planning and Billing

ANALYST / PLANNING ENGINEER, M4 Contracting SARL, Radar Buidling at Al Ain International Airport

START Date: 
July, 2015

Airports Projects- Primavera P6, Project Management, Risk Management, Project Planning and Billing

ANALYST / PLANNING ENGINEER, Arabtec Construction Dubai LLC, HEAD OFFICE

START Date: 
November, 2015

General Planning Engineer

Analyzing site work and deriving possible causes of delays

ANALYST / PLANNING ENGINEER, Al-Rushaid Construction Company, Power Plant

START Date: 
June, 2009
END Date: 
September, 2015

AL-RUSHAID CONST. CO., LTD.      Rabigh Independent Water, Steam &     Sr. Planning Engr II                                  

Jan 2013 – Sept 2015                         Power Plant, Rabigh, KSA

Experience Hours (Planning & Scheduling): 
12000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
12000

ANALYST / PLANNING ENGINEER, Enron, Dabhol LNG Project

START Date: 
July, 1999
END Date: 
October, 2001

Project – Construction of LNG Terminal for 2184MW Dabhol Power Project, Maharashtra

Client – Dabhol Power Company

Project Description – 2184 MW combined cycle power project, LNG receiving terminal and re-gasification facilities of 5MMTPA capacity. Scope involved 3x160,000 M3 LNG Storage Tanks, Marine Terminal and 2 km Jetty with LNG unloading facility, Breakwater construction and re-gasification facilities, OSBL piping for natural gas supply to power block and commercial usage.

Experience Hours (Planning & Scheduling): 
4350

ANALYST / PLANNING ENGINEER, Toyo Thai co.,ltd, LDPE Polyethylene Plant,

START Date: 
October, 2007
END Date: 
April, 2012

2010 to 2012 Planning Engineer Toyo-Thai Corp.,Ltd ,
Vinythai Windmill ABT Project, Rayong Thailand
2007 to 2010 Project control Toyo-Thai Corp.,Ltd
 PTT - PTTPE –LDPE Project, Rayong Thailand

• Developing and updating the EPC schedule by using Primavera Project Planner P5.
• Developing detailed schedules and issuance (Three Weeks Look Ahead schedules, 90 days look Ahead Schedules).
• Responsible in Project planner team for detailed and control schedule as per target on Shut down and Turnaround work.

Experience Hours (Planning & Scheduling): 
12000