Quintin Walker

First Name: 
Quintin
Last Name: 
Walker

Over 18 years’ experience within the project controls environment focusing on the planning and scheduling of major programs and projects, implementation over its entire life cycle, with additional experience gained in the areas of project risk management, contract management, claim management, reporting, governance and development and implementation of process and procedures related to project controls.

Key technical competences include:

Professional Since: 
Jan-2000 (24.8 yrs experience)
Oldest experience: 
Jun 2007 (17.4 yrs experience, WARNING: 7.4 years variance with Professional Since)
Years Experience: 
12

Sr. Project Control Engineer, Projacs International/Egis, Abha Regional Airport Development Project

START Date: 
November, 2016
END Date: 
March, 2018

Package: (1,791,769,864.00 S.R. Contract Value):

  • This Package includes original scope of the contract that includes the construction of the following facilities in an existing airport, Airside Works, External Works, Bridges, Retaining Walls, Facilities & Utilities, Building Works, Passenger Terminal Buildings, and Renovation of existing Buildings & Meteorology Facilities.

Duties & Responsibilities:

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000

Christopher Bates

First Name: 
Christopher
Last Name: 
Bates

Cost and Schedule SME major infrastructure including Roads, Rail, Water, Airfield

Production Rates 

Methodology 

Efficiency Savings 

Carbon Footprint

Innovation

Value Management 

Professional Since: 
Sep-1985 (39.2 yrs experience)
Years Experience: 
0

James Mulhearn

First Name: 
James
Last Name: 
Mulhearn

Mr. Mulhearn's experience covers over 30 years of practical and managerial assignments in Project Management, Construction Management, Cost Control, Quality Assurance, Quality Control, Scheduling, Equipment Operations, Maintenance, Rehabilitation, Procurement, Evaluation and management of Major Transportation (Road - Rail & Aviation) projects in Asia, Africa, Latin America, the United Kingdom and the USA.  

Professional Since: 
Jan-1980 (44.8 yrs experience)
Oldest experience: 
Jan 1980 (44.8 yrs experience)
Years Experience: 
39

Prototype Wireman, Zental Performances, (various projects) @ all UK

START Date: 
April, 1985
END Date: 
August, 1985
Zental Performances, Bourne End Prototype Wireman Wiring and assmebly of satellite equipment. Great place to work fun and friendly.

Senior Project Controls Manager - North West - ref 6734, Hill International, LAX Midfield Satellite Concourse Program

START Date: 
May, 2015
END Date: 
October, 2017

Implement an integrated system of project controls and dashboard reporting system to manage the $1.6 billion-dollar program to construct the new Midfield Satellite Concourse North at LAX. Provide oversight and management to the estimating, cost, scheduling, and document control professionals supporting the program. 

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
1000

Project Controls Manager, AECOM, King Khaled International Airport Riyadh

START Date: 
October, 2018
END Date: 
February, 2019

As project controls manager/lead planning engineer I am responsible for managing cost and time of all projects under the PMCM services.My role involves  :-

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
5000
Experience Hours (Forensic Analysis): 
2000

Planning Engineer & Quantity Surveyor, Taisei TAV Sky Oryx Joint Venture, Hamad International Airport CP18 – Passenger Terminal Complex

START Date: 
July, 2007
END Date: 
January, 2012

July 2008 to January 2012

Experience Hours (Planning & Scheduling): 
7000
Experience Hours (Cost Management): 
2000

MATT IVANOFF

First Name: 
MATT
Last Name: 
IVANOFF

I am a Project Controls Manager within the Aerospace manfuacturing field.  My experience is derived from commercial aircraft interior manfuacturing.  I have spent time as a material planner, configuration planner, planning engineer, and project controls manager.

Professional Since: 
Mar-2012 (12.7 yrs experience)
Oldest experience: 
Mar 2012 (12.7 yrs experience)
Years Experience: 
48

Configuration Planner, Material Planner, Planning Engineer, Project Controls Manager, CFW PRECISION METAL COMPONENTS, Aircraft Interior manufacturing

START Date: 
March, 2012

Material Planner: 

  • Analyzed and ordered all required material while utilizing beneficial purchasing techniques (order policies, period orders, etc.) with respect to inventory turns, cost, and lead times.
  • Initiated and implemented facility wide processes which successfully lowered inventory while decreasing shortages on the production floor. Order policies, Period orders, safety stock , etc…

Configuration Planner:

Experience Hours (Planning & Scheduling): 
14000
Experience Hours (Cost Management): 
8000