Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Spain

PRINCIPAL PLANNING ENGINEER , SENER INGENIERIA Y SISTEMAS, Tres Cantos (Madrid), Spain, BP Oil New Port Facilities of Castellón (Spain), LNG Dunkerque EPC, Underground Railway of Panama,LRT/Tram Project of Light Rail Train/Tramway of Abu Dhabi (UAE)

START Date: 
May, 2010
END Date: 
June, 2011

BP Oil New Port Facilities of Castellón (Spain)- Refinery Revamping, Interconnecting Works and New Port Facilities for maritime loading & unloading HC products. Project asset budget of 50 Million Euros.

LNG Dunkerque EPC project of Regasification plant of Dunkerque (France)for EDF (Electricité de France). Investment Budget of 900 Million Euros.

Underground Railway of Panama- Detail Engineering & Auxiliary Systems of the underground railway.

Principal Planning Engineer, SENER INGENIERIA Y SISTEMAS, Spain, Tres Cantos (Madrid), BP Oil New Port Facilities of Castellón (Spain), LNG Dunkerque EPC, LRT/Tram Project of Light Rail Train/Tramway of Abu Dhabi (UAE), Underground Railway of Panama

START Date: 
May, 2010
END Date: 
June, 2011

BP Oil New Port Facilities of Castellón (Spain)- Refinery Revamping, Interconnecting Works and New Port Facilities for maritime loading & unloading HC products. Project asset budget of 50 Million Euros.

LNG Dunkerque EPC project of Regasification plant of Dunkerque (France)for EDF (Electricité de France). Investment Budget of 900 Million Euros.

Underground Railway of Panama- Detail Engineering & Auxiliary Systems of the underground railway.

Piping Engineer - Engineering/Fabrication, planning engineer, AGD II -- Bechtel in Asab, UAE: ETP 2nd phase -- TecnicusReunidas, Spain, Ruwais refinary expansion project-II, Qatar Petroleum, Halliburton, NDC

START Date: 
April, 2007
END Date: 
September, 2013

Hi,

I am Syed Imtiaz, 45, 8 years in Oil Gas sector,  presently working as a factory engineer in a organization called Al Mansoori in Abu Dhabi, UAE.

My Role and responsibilities are to run the workshop with limited manpower safely and effectively as well as planning the on going projects and up coming projects. And every sunday (first day of the week in UAE ) I need to produce the project status in the weekly project review meeting, discussing mostly the task which is not according to the dates and % completed mentioned in the gantt chart. 

Fernando Rodríguez González

First Name: 
Fernando
Last Name: 
Rodríguez González

Senior Planner Manager with experience in singular buildings scheduling, roads, railways and metros.

Multiproject analysis and economic management.

Team management experience.

Risk analysis skills and multicriteria decision analysis.

Professional Since: 
Jul-1989 (35.0 yrs experience)
Oldest experience: 
May 1990 (34.2 yrs experience, WARNING: 0.8 years variance with Professional Since)
Years Experience: 
21

Area Planning Manager and Cost Manager, Government of Andalusia, Spain, metros and other infraestructures managed by autonomic government of region andalusia, railways, Roads, Spain

START Date: 
November, 2011

Senior Planner Manager with experience in singular buildings scheduling, roads, railways and metros. Multiproject analysis and economic management. Team management experience. Risk analysis skills and multicriteria decision analysis.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content