Sir Alfred McAlpine (botswana Pty)

Site Agent, Sir Alfred McAlpine (Botswana Pty), Selebi Phikwe Reservoir

START Date: 
May, 1985
END Date: 
December, 1986

Plant, & Labour control and all disciplines concerned with the construction of a civil engineering project

Section Engineer, Sir Alfred McAlpine (botswana Pty), Morupule Power Station

START Date: 
July, 1983
END Date: 
July, 1985

Section Engineer responsible for RC works at Morupule Power Station. Design of concrete mixes and batching plant output control and regulation.