Posted Thu, 2011-01-13 09:08 by Carumbaiah Kolli...
START Date:
February, 2008
END Date:
March, 2010
Preparation of Baseline Schedule
Monitoring progress as per Schedule
Preparing and revising Labour Histogram based on tender manhours and actual output on site.
Preparation of fortnightly look ahead program
Revising construction programs to include additional works and incorporate delays and extension of time.
Preparing Schedule related documentation and attending meetings with client / consultant for successful claim for extension of time of 100 days in a 15 month project.
Review of subcontractor program and coordination with subcontract