Nasser S Al-Hajri Corporation

Planning and Project Controls Engineer, Nasser S Al-Hajri Corporation, JERP

START Date: 
February, 2010
END Date: 
February, 2012

·         Created/Updated Project Schedules (Level 3 & 4) using Primavera 6/ MSP

·         Defined WBS and monitored the progress of the same at WBS Levels

·         Assisted in Preparing budget and Predicting Cash Flows

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
1500

suni surendran

First Name: 
suni
Last Name: 
surendran
Professional Since: 
May-2008 (16.6 yrs experience)
Oldest experience: 
Feb 2016 (8.8 yrs experience, WARNING: 7.8 years variance with Professional Since)
Years Experience: 
46

Lead Planning Engineer, Nasser S Al-Hajri Corporation, Sadara Project (HP-LDPE)

START Date: 
February, 2016
 Presently Working for Sadara Petrochemical Industry jubail, Dammam, KSA deputed by Nasser Al Hajri Corp as lead Planning Engineer from 12th October 2011 to till date. Assigned site and job description: I am a part of project management team & responsible for project construction as well as     planning & scheduling management and overall project control. To study the project IFC drawings and determine the construction sequence of activities.
Experience Hours (Planning & Scheduling): 
14700
Experience Hours (Cost Management): 
12750
Experience Hours (Forensic Analysis): 
9750

Planning Engineer, Nasser S Al-Hajri Corporation, Raz Al-Khair Aluminium Smelter Plant Project

START Date: 
August, 2010
END Date: 
March, 2012

 

Activities & Responsibilities:

§  Project Progress Monitoring

§  Scheduling

§  Planning & Intra discipline Co-Ordination

§  Quantity take-off

§  Development of Progress Measurement System

§  Preparation of Engineering Reports

§  Database Controlling by Updating the Progress in MS Access

Shebin Thomas

First Name: 
Shebin
Last Name: 
Thomas

 Myself, Shebin Thomas, currently employed as a Planning and Scheduling Engineer in an EPCI organization dealing with all planning aspects of the running project. My main areas of working covers the following:

Professional Since: 
Nov-2009 (15.0 yrs experience)
Years Experience: 
0