Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Jurong Shipyard Pte Ltd

Structural and Coating Lead, Jurong Shipyard Pte Ltd, Modec OSX3

START Date: 
December, 2011
END Date: 
November, 2013
Executed the construction portion of project plans through micro planning and ensured that siteprogress is aligned with project’s overall schedule. Led a team of multi-discipline supervisors to monitorand provide guidance to sub-contractors on day-to-day direction of site activities. Ensured smooth andsafe execution of site work.

Structural and Piping Lead, Jurong Shipyard Pte Ltd, Petrofras P62

START Date: 
June, 2010
END Date: 
November, 2011
Executed the construction portion of project plans through micro planning and ensured that siteprogress is aligned with project’s overall schedule. Led a team of multi-discipline supervisors to monitorand provide guidance to sub-contractors on day-to-day direction of site activities. Ensured smooth andsafe execution of site work.

Piping and Mechanical Lead, Jurong Shipyard Pte Ltd, Noble Jim Day

START Date: 
June, 2008
END Date: 
June, 2010
Executed the construction portion of project plans through micro planning and ensured that siteprogress is aligned with project’s overall schedule. Led a team of multi-discipline supervisors to monitorand provide guidance to sub-contractors on day-to-day direction of site activities. Ensured smooth andsafe execution of site work.

PLANNING ENGINEER, Jurong Shipyard Pte Ltd, Maersk Convincer; Petrojack IV; Atwood Osprey; Seadrill West Elara

START Date: 
February, 2008
END Date: 
October, 2010

Schedule Setup

Setup Schedule based on Contract WBS in line with company planning policies and guidelines.

Usage of Manpower / KPIs to determine durations of activities and to plan for construction sequencing.

Setup of physical progress measurement using key measurables (Steel Tonnage / Pipe Spools / Cable Length / Termination points etc)

 

Schedule Analysis and Control / Problem Solving

Conduct weekly analysis of schedule (Float, Critical Path, Manpower, Resource)

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
250

Market Place

No results found... (try selecting a different content filter)

Syndicate content