Rates, Norms & Durations

howlong.jpgWhat is needed to come up with a production rate?

A duration of time, the manhours involved, and an amount of work produced?

This section is here to document this.  What information do you have that you can share?

Comments

Member for

14 years 4 months

Hi Frendz ...

I like this section this is helping me in may ways ..but i am facing problem when it comes to productivity rates given without resources, as what resource  should i consider if i want to use these rates please help .......

 

 

regards,

Khan

Member for

13 years 3 months

Hi all,

 

I am also facing problem in sourcing MEP labout production rate for Middle East Region. Anyone can help?

 

regards,

 

Kevin

Member for

14 years 4 months

 

S.N0

Activity

Productivity norms

Qty

Units

DUCTING:

1

Duct

1.2 – 1.5

Sqm/man/day

2

Insulation

3

Sqm/man/day

3

1 No - VAV

3

Sqm/man/day

4

1 No - ECV

2

Sqm/ man/day

5

1 No – Joint Insulation

0.4

Sqm/man/day

6

1 No - Flexible Duct

1

Sqm/man/day

7

1 No - Plenum

1

Sqm/man/day

8

1 No - MSFD

2

Sqm/man/day

9

1 No - VCD

1

Sqm/man/day

10

Pressure Test per 25 Sqm ducting

4.5

Sqm/man/ day

11

Multipurpose Supports – 4 No

1.5

Sqm/man/day

12

Grills & Diffusers

6

No’s / Man/ day

13

Linear Slot Diffuser

6

Rm / Man / day

 

Kindly note that here ducting  is inclusive Support fixing + Cleat fixing + Sealant application

CHW PIPE:

1

1" – 2" dia

7.5

Rm/man/day

2

2" - 3"dia

5

Rm/man/day

3

4"dia

2.5

Rm/man/day

4

6"dia

1.5

Rm/man/day

5

8"dia

1.2

Rm/man/day

6

10"dia

1

Rm/man/day

7

CHW Pipe Insulation

15

Rm/man/day

8

Pressure Test for 100 Rm

3

man/day

9

Valve Package

1.5

Man / day / unit

 

Kindly note that here Chilled water piping is inclusive of Support fixing

S.N0

Activity

Productivity norms

Qty

Units

ELECTRICAL/ELV

1

Conduit

16

Rm/man/day

2

Wiring

30-40

Rm/man/day

3

Cable tray

5-6

Rm/man/day

4

Trunking

8-10

sq.m/man/day

5

DB Installation

1

Nos/man/day

6

DB Termination

1

Nos/man/day

7

Final Fix Accessories

8

Nos/man/day

8

Light points

8

Nos/man/day

PLUMBING

1

Water supply pipe installation

5

Rm/man/day

2

Drain pipe installation

3

Rm/man/day

Kindly note that Piping Installation is inclusive of Support fixing

Member for

16 years 11 months

Hi Guys,

 

Just like to know if we have productivity rate for glazing partitions..... also there is no productivity rate for plasterboard installation on the partitioning rates.

 

Thanks!

 

Ruel

Member for

11 years 9 months

 

 

Can anyone help me with the units used to measure progress of platfrom fabrication & welding?

 

Is it ok to USE ... Kg of steel fabricated or welded?

Member for

11 years 9 months

 

 

Can anyone help me with the units used to measure progress of platfrom fabrication & welding?

 

Is it ok to USE ... Kg of steel fabricated or welded?

Member for

14 years 6 months

Good Morning,

 

The information avaialble here is very useful for me, thanks a lot.

I will be very thankful if excel file or PDF file of all prodcution rates can be shared on my email address: lnt.vikas@gmail.com

Thanks,

Vikas Budhiraja, PMP

Member for

11 years 2 months

Dear all experts,

 

I need the productivity rates for first and second fixs for MEP work (HVAc, Firefighting and Plumbing).

 

Thank you

Member for

11 years 2 months

Dear all experts,

 

I need the productivity rates for first and second fixs for MEP work (HVAc, Firefighting and Plumbing).

 

Thank you

Member for

10 years 9 months

Thank you deeply, for the great effort you've been doing.

I just would like to pay your attention that the productivity rates are in a big need to the crew structure producing these rates.

 

Best Regards,

Member for

10 years 9 months

Thank you deeply, for the great effort you've been doing.

I just would like to pay your attention that the productivity rates are in a big need to the crew structure producing these rates.

 

Best Regards,

Member for

10 years 9 months

Thank you deeply, for the great effort you've been doing.

I just would like to pay your attention that the productivity rates are in a big need to the crew structure producing these rates.

 

Best Regards,

Member for

10 years 6 months

Can i get the production rate dia Inch for CHW pipes for example 20" pipe one joint require 3 hours .. Etc or if there is a formula followed to calculate the same knowing that its all sch STND

Member for

11 years 4 months

Dear all experts,

 

I need the productivity rates for Oil & Gas Project - Construction Trade like Sand Blaster, Fireproofer, Spray Painter, Scaffolder, Sheet Metal Fitter, Insulators and Welder.

I will be very thankful if excel file or PDF file of all production rates can be shared on my email address: sukh_shrestha@hotmail.com

Thank You

Member for

10 years 7 months

Dear all experts;

This data is very useful for me and thank you all. But i need construction labour rates as an excel file. If somebody has it and sen me i will very be thankful. Also can you please give a book advise for this issue.

Thank you all.

efe.gurkan@hotmail.com

Member for

19 years 8 months

Are you in need still?

Jaocb Armstrong JEPM LLC  409-457-7725

Member for

13 years 3 months

Ya, I am waiting for comments. If you can give some feedback/ comments, it will greatly be useful.

Thanks/Regards,

Santhosh

Member for

19 years 8 months

Are you in need still?

Jaocb Armstrong JEPM LLC  409-457-7725

 

Member for

19 years 8 months

What geographical location is labor being executed? (remote/local port)

What is the weather conditions?

What type of industry?

Other particulars or need; Are there readily available resource (MP & DFL Equip/Consumables) ?

Please feel free to contact me at your convenience. 

Once we come into mutual agreement, I will produce the needed excel loaded unit rates for your project/s need/s.  Based on execution industry actuals.

Best regard,

JEPM LLC

Project Controls Engineer SME

Jacob Armstrong

409-457-7725

Member for

10 years 2 months

I am struggling to see any logic behind the productions per hour on the drainage?

33m per hour for 150mm drainage in runs exceeding 30m or greater is impossible - unless installed via trenchless methods!

I calculate my drainage productions to include dig, bed and surround, pipe laying and backfilling compacting in accordance with the specification and would never price on more than 30 - 35m per DAY for a 150mm UPVC pipe at a depth not exceeding 1m.

What do the productions on here realte to and what do they include?

Member for

12 years

looking at the drainage outputs on here they don't seem to be that reliable? does anybody have an excel spreadsheet they would be able to send with some general drainage outputs?

Member for

8 years 8 months

Hi,

It seems that the most of the rates here are equipment rates. do you have any rates for manpowered activities (e.g. manual excavation)

Member for

8 years

MEP productivity rate norms::

Does anyone know where to get the Productivity rate of MEP work that trust worthy and can be used as reference to support the duration calculation. 

greatly appreciate,

pisan_osk@hotmail.com

Member for

7 years 10 months

Hi, Has anyone got any information of Metsec output rates please

Member for

11 years 3 months

Hello sir,
If you have any data related to MEP activities productivity rates for gulf countries, request you to kindly share on nimish93@gmail.com

Regards,
Nimish R Swami

Member for

4 years 8 months

Hello all 

Im new to this platform but am looking for some output rates for sprinkler installations in the UK. any and all help will be apprecieated

Member for

18 years 6 months

For your requirement lads,

Activity DescriptionODResource DescriptionQuantity DescriptionMan/day total mandayBOQ QuantityUnitsProductivity (Units/Mandays)Antitermite & Blinding2Formwork LabourBlinding Concrete4.0845.54m²22.77Footings Concrete Works3Unskilled Labour 3.09    Formwork LabourFormwork area as executed5.01547.84m²3.19 Steel FixerReinforcement Steel6.0183ton0.17Backfill & Compaction4Unskilled Labour 3.012   MEP Works Below Grade Slab3PlumberPipes4.01255m4.58 ElectricianUnderground Cables4.01255m4.58Grade Beams Concrete Works3Unskilled Labour 3.09    Formwork LabourFormwork area as executed6.01897.32m²5.41 Steel FixerReinforcement Steel5.0152ton0.13SOG Concrete Works4Unskilled Labour 2.08    Formwork LabourSlab on Grade2.0822.74m35.50 Steel FixerReinforcement Steel6.0243ton0.17Water Tank FN Concrete Works4Unskilled Labour 1.04    Formwork LabourFormwork area as executed0.31.26.28m²5.23 Steel FixerReinforcement Steel2.081ton0.13Water Tank Walls Concrete Works4Unskilled Labour 2.08    Formwork LabourFormwork area as executed4.01684.44m²5.28 Steel FixerReinforcement Steel2.081ton0.131st Flr. Column Reinforcement & Concrete2Unskilled Labour 4.08    Formwork LabourFormwork area as executed10.02090m²4.50 Steel FixerReinforcement Steel4.081ton0.131st Floor Slab & Staircase Concrete Works4Unskilled Labour 5.020    Formwork LabourFormwork area as executed10.040213.62m²5.34 Steel FixerReinforcement Steel7.0284ton0.14Rf Flr. Column Reinforcement & Concrete2Unskilled Labour 5.010    Formwork LabourFormwork area as executed10.02077.52m²3.88 Steel FixerReinforcement Steel4.081ton0.13Roof Floor Slab Concrete Works3Unskilled Labour 5.015    Formwork LabourFormwork area as executed10.030155.8m²5.19 Steel FixerReinforcement Steel9.0274ton0.15Parapets & Upstands3Formwork LabourConcrete4.012   Blockworks w. Accessories66Unskilled Labour 8.072    MasonBlockwalls8.0722780m²5.27 Scaffolder 0.54.5   Plaster + Subframes7Unskilled Labour 4.028    PlastererInterior Plaster6.545.5545m²11.98Waterproofing Wet Areas5Waterproof labourWet Area Waterproofing2.010   Primary Painting5PainterFirst Coat Paint11.055692m²12.58Wall Tiles5Tile WorkerCeramic Wall Tiles4.020128m²6.40Pantry Units3Carpenter / JoinerPantry Cabinets1.031item Interior Doors & Ironmongery5Wooden Door FixerWood Doors2.01016No1.60Floor Tiles7Tile WorkerCeramic Floor Tiles4.028216m²7.71False Ceilings & Furrings7Suspended Ceiling LaborSuspended Ceiling7.049980m²20.00External Windows & Doors7Alum. Works JoinerAlum. Windows / Doors3.02126No1.24Kitchen Cabinets5Carpenter / JoinerKitchen Cabinets/Units1.051item0.20Vanity Counters / Cabinets3Carpenter / JoinerVanity Cabinets/Units1.031item0.33Wardrobes5Carpenter / JoinerWardrobes1.051item0.20Vanity Tops2Carpenter / JoinerVanity Cabinets/Units1.021item0.50Final Coat of Paint4PainterFinal Coat Paint5.020692m²34.60Shower Enclosures3Carpenter / JoinerShower Enclosures1.031item Roof Steel Structure14Joiner Steel WorksStructural Steel4.056   External Rendering14PlastererExterior Plaster4.056610m²10.89 Scaffolder 1.014   Thermal & Moisture Protection @ Roof7Waterproof labour 2.014198m²14.14External Paint7PainterExternal Paint7.049610m²12.45Boundary Wall & External Civil Works21MasonBlockwalls0.36.355m²9.00 Formwork LabourFormwork area as executed1.531.5107m²3.50 Steel FixerReinforcement Steel0.613.32ton0.15 PlastererExterior Plaster0.612180m²15.00 PainterExterior Paint0.612180m²15.00Handrails & Balustrades5Carpenter / JoinerInt. Handrail / Balustrade4.02023m1.20GRC Installation10GRC FixerGRC6.060   Domestic Piping & Valves6PlumberPipes4.024298m12.42Drainage Piping5PlumberPipes2.010133m13.30Domestic Water Pumps & Access.7PlumberPipes0.21.4   Water Heaters2PlumberPipes1.02   Ductwork & Insulation7Ductwork LabourDuctwork5.0351530kg43.71Fuel Gas System7PlumberPipes1.0712m Split Systems5Ductwork LabourSplit Units1.899No1.00Exhaust Fans3Ductwork LabourExhaust Fans1.035No1.67Grilles & Diffusers3Ductwork LabourAir Outlets / Grilles2.0639No6.50Sanitary Wares3PlumberSanitary Wares3.0939No4.33Electrical Ducts & Conduits4ElectricianWires & Cables5.020   Home Automation Conduits2ElectricianWires & Cables2.04   Wiring & Cable Pulling5ElectricianWires & Cables6.03046m1.53Installation & Termination of DBs / Panels5ElectricianDBs1.052No Lighting Fixtures & Detectors3ElectricianLighting Fixtures5.015133No8.87

Member for

1 year 11 months

Kindly send productivity rates of asia also, and mention more activitiese