· Lay sand and cement floor screeds to accurate levels and finish with steel/wood float. Rate apply to a gang or 2 labourers and 1 screeder with materials being delivered by hoist and barrow. |
Thickness -> | 15 to 20mm 4.85 | |
20 to 30mm 4.63 | ||
30 to 40mm 4.17 | ||
40 to 50mm 3.79 | (Ave4.50,BestRate 5.26) | |
50 to 65mm 3.29 | ||
65 to 100mm 3.00 |
· Underground rooms with poor lighting and ventilation, a typical rate of 1.63 m2/hr. This rate achieved by labour only subcontractors and hence is very slow. |
· Typical rates for fixing of the floor screed battens, for tamping of screeds etc. |
Fix 10.0 m/hr |
Strike 20.0 m/hr |