Revision of Sand / Cement Floor Screeding from Mon, 2009-08-10 10:20

·         Lay sand and cement floor screeds to accurate levels and finish with steel/wood float.  Rate apply to a gang or 2 labourers and 1 screeder with materials being delivered by hoist and barrow.

Screeding Rates (m2/hr)

Thickness  ->   15 to 20mm 4.85  
  20 to 30mm 4.63  
  30 to 40mm 4.17  
  40 to 50mm 3.79 (Ave4.50,BestRate 5.26)
  50 to 65mm 3.29  
  65 to 100mm 3.00  
                                                      

·         Underground rooms with poor lighting and ventilation, a typical rate of 1.63 m2/hr.  This rate achieved by labour only subcontractors and hence is very slow.  
  

·         Typical rates for fixing of the floor screed battens, for tamping of screeds etc.
      Fix       10.0 m/hr
      Strike    20.0 m/hr