Small Scale Spread and Level By Hand

Including load and wheel an average of 20 m from tipped heap (m3/hr) 
Layers ->n.e.25mm25-75mm75.200mmExc.200mm
Sand/Soil    
n.e. 200 m21.031.031.121.23
exc. 200 m21.371.371.491.64
Gravel/Shingle    
n.e. 200 m2 -0.860.931.03
exc. 200 m2 -1.141.231.37
Hardcore    
n.e. 200 m2 -0.851.021.27
exc. 200 m2 -1.021.271.69
  Spread and Level By Crawler Shovel  Rates in (m3/hr) 
Machine Bucket->0.6m30.8m31.0m31.2m3
Sand/Soil    
n.e. 200 m218.6738.4643.4852.63
exc. 200 m224.3950.0055.5666.67
Gravel/Shingle    
n.e. 200 m218.8738.4643.4852.63
exc. 200 m224.3950.0055.5666.67
Hardcore    
n.e. 200 m215.8731.2537.0443.48
exc. 200 m219.2340.0047.6255.56
Clay    
n.e. 200 m217.2435.7143.4847.62
exc. 200 m222.2245.4555.5662.50

Note:

  • n.e means "not exceeding"