Revision of Breaking Out from Sun, 2009-02-22 09:46

Concrete And Remove (hrs/m3)

 

  Depth Hand Machine
Slabs - unreinforced Ne 50 mm 2.35 1.96
  50 - 100 mm 3.15 2.46
  100 - 200 mm 3.75 3.94
  200 - 300 mm 4.12 5.55
Slabs - reinforced Ne 50 mm 4.71 3.92
  50 - 100 mm 5.52 4.32
  100 - 200 mm 5.88 4.71
  200 - 300 mm 6.12 9.09
Walls - unreinforced all walls 4.71 3.04
Walls - reinforced all walls 5.52 3.92
Beams - reinforced all sizes 7.50 5.89
Columns - reinforced all sizes 9.20 7.30
Foundations - unreinforced all sizes 3.60 3.00
Foundations - reinforced all sizes 5.40 4.80

 

Breaking Out Tarmac

Rates include for breaking out and removal of rubble (hrs/m3).

  Depth Hand Machine
Pavings Ne 50 mm 1.96 1.56
  50-100 mm 2.08 1.64
  100-150 mm 2.17 1.75
Roadways upto 150 mm   3.57

Breaking Out Brickwork

Rates include for breaking out and removal of rubble (hrs/m3).

  Depth Hand Machine
Walls/columns Ne 100 mm 2.40 1.38
  exc 100 mm 2.75 1.57
Foundation all sizes 2.75 1.57