To setup a cofferdam dewatering system, including boring, pump installation and outflow pipework and drainage tanks etc, typical rates are...
- Small 2 hole system, for an overrun tunnel, with a single drilling rig takes about 7 - 10 days to get up and running.
- A larger system, with 10 - 15 holes, for a station type cofferdam will take in the region of 3 weeks with 2 rigs. This can be speeded up with the use of more rigs to reduce the well boring times.