Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Revision of Sheet Piling from Fri, 2009-02-06 06:56

Sheet Piling On reclamation, sand fill, sheet piling by crane and drop hammer, vibro hammer or diesel hammer.
  • A rate of 20 - 25 No/day to 20 to 35 m deep.
  • 1 no = 0.4 m wide on plan and 6 m long.
  • Therefore 8 - 10 m/day per rig is achievable.
On more difficult areas, such as through existing ground or a sea wall for example.
  • A rate of 10 - 12 No/day to 20 m deep.
  • Therefore 4 - 6 m/day per rig is achievable.
For more shallow sheet pile walls
  • Driven by - Pilemaster 60.0 m/day
  • Driven by - Automatic Drop Hammer 32.0 m/day
Steel for piles is usually readily available and a two week lead in is often all that is required.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.