Project Controls Manager, Tecnicas Reunidas, DHP and CCR
Working as EPC contractor for an onshore brownfield revamping project that included a new Diesel Hydro Processing unit (DHP), Amine Regeneration Unit (ARU), Sulphur Recovery Unit (SRU), Sour Water Unit (SWU), and 2 new Cooling Towers- one chemical and one natural draft. Additionally, an intense brownfield upgrade of the existing steam generation boilers, new turbo-generators, installation of new control room, and tie-in into existing operating plant. This was a Joint Venture between Tecnicas Reunidas, GS (formerly LG), Alarko, and Gama with TR and GS being responsible for engineering whole Alarko and Gama were responsible for construction in their respective areas. My primary duty was as Project Controls Manager and secondary duty as Assistant Site Manager for Tecnicas Reunidas.
Primary duties included:
Development of Master project schedule and incorporation of partner level 4 Construction schedule.
Progress update for monthly report as well as bi-weekly S curves per discipline, based on physical installed quantities. Re-measurement of quantities from drawings.
Progress verification based on executed quantity by either physical verification or as measured on the drawing.
Development and management of field change control procedure.
Development of shut-down schedule for area 4 (boiler and generator installation area).
Cost reporting and cost forecasting, including CPI analysis.
Preparation of applications for payment and invoices, as well as follow-up with client.