Planning & Project Control Engineer, ARCHIRODON CONSTRUCTION (OVERSEAS), & Power infrastructure works and 132kv/66kv substation distibution station
START Date:
July, 2010
END Date:
April, 2011 • Developed comprehensive baseline CPM schedule.
• Responsible for opening, updating and closing cost centers of the project.
• Allocated the resources for activities and calculate productivity of projects.
• Updated schedules and analyzed manpower and cost allocations.
• Cost Estimation.
• Maintained a report of actual cost against estimated budget for all current projects at the site operations and submitted it monthly.
• Forecasted the estimate at completion to anticipate the cost trend of the project.
• Conducted CPM meetings to present information to subs and owners.
• Generated narrative reports.
• Time Impact Analysis.
Experience Hours (Planning & Scheduling):
1500
Experience Hours (Cost Management):
300
Experience Hours (Forensic Analysis):
100 - Company: