Project Manager, Exterran, Oak Grove and CRPs

START Date: 
June, 2012
END Date: 
September, 2013

Responsible for earthwork and construction of the pad (7.1MM cubic yard of earthmovement) and delivery of first 200MMSCFD equipment and balance of plant engineering. Scope managed was Engineering, Procurement, and Construction Management of three trains of 200MMSCFD Cryogenic trains with balance of plant, with planned built-out capacity of 2BSCFD. Key achievement was selection of EPC subcontractors for scope that was not self-performed.

Responsible for engineering, construction and commissioning of 23 locations (scattered through in Marcellus shale region in West Virginia and Ohio) for handover to client's Operations and Maintenance Team.  These facilities are part of a gathering system in the Marcellus Shale region, which feeds to a central processing facility.  Scope managed varies for each location: from upgrading current installation to increase flow, to location selection with scope of earthwork construction to equipment selection and installation only.