Planning Engineer, Aljaber, Ware house construction,

START Date: 
May, 2015
  1. Develop the Baseline schedule in line with contract specifications, drawings and BOQ items with cost.
  2. Detailed micro scheduling and estimating of quantities, resources and duration of activities
  3. Tracking & controlling the baseline schedule indicating project schedule performance (EV/PV)
  4. Preparing the daily, weekly & monthly progress reports for consultant and management
  5. Develop the Project S-curve budget, resources plan/histogram, expenditure & forecast bill
  6. Prepare and submit the monthly bill or invoice for payment.
  7. Update & analyze the baseline to determine and highlight Areas of Concerns for consultant approval
  8. Prepare delay analysis using impacted as planned, time impact analysis, window analysis, as-planned vs. as-built and collapsed as-built for extension of time & compensation
  9. Evaluate and report the time impact of additional work, change orders and variation on baseline for extension of time
  10. Review, monitor and control subcontractor task on the baseline to achieve project completion date.
  11. Prepare weekly and monthly project status for management review and action
  12. Prepare lesson learnt report during project close out documentation.