Assistant Cost Engineer, IVRCL, Building Projects
Working Experience:-
Jr. Engineer (Cost Control/ Planning)–Civil (May 2011 to Till Date)
IVRCL Limited,
Projects:
1. Ext. of Bihar Vidhansabha & Secretariat Blocks Project, Patna, Bihar
2. External Plumbing, Firefighting & Landscape works under the Ext. of Bihar Vidhansabha & Secretariat Blocks Project, Patna, Bihar..
3. Construction of Remaining works at VID Project.
4. Extension of High Court project, Patna.
My Responsibilities:
As a Cost Control Engineer.
vDevelop a project tracking system either based on existing tools or self developed that allows for project portfolio management including cost tracking of all projects against a fixed annual budget, prioritization of project portfolio, tracking of deferred .
vMaintain and communicate projects budgetary and completion status’ through all phases
vReport monthly project costs and identify critical issues.
vProvide project scheduling, cost control, and other project support functions and activities, as instructed by management.
vCreate, maintain, update, and analyze project and schedules and budgets.
vForecast costs at completion, management of change, cost estimating, and issuing reports to the Project Team and Management, as required.
vResponsible for setting up the control systems for the projects to record, maintain and report original and current schedules, budgets, pending/approved/rejected changes and budget transfers, actual expended, estimate-to-complete, estimate-at-completion amounts, and their variances against control budgets, and work progress and productivity values.
vTrack and incorporate out of scope work activities, securing management approval, assisting in the review of invoices, and maintaining change order logs.
Ø As a Planning Engineer
vPrepare bar charts by using MSP at appropriate intervals.
vMaintained excellent operational contact with all member.
vMaintaining all records in different files.
vTo Prepare a deviation statements as per approved ACE vs Expenduture.
vTo Prepare a comparatives statements
vTo prepare the work orders
vTaking Quotation for Different vendors.
vTo prepare the turnover Projections & Given to Project- In- Charge and Site – In- Charges
vTo prepare the list of Materials and Man-Power Required
vTo Prepare the Purchase indents and same forwarded to Regional offices
vTo Prepare Cash Flows
vTo Prepare the Daily Progress & Weekly Progress Reports
vTo Prepare Monthly reports and same submitted to Project – In-Charge
vTo Prepare Monthly MIS Reports.