SENIOR ENGINEER (Contracts & Construction Management Division) , ENGINEERING CONSULTANCY SERVICES PUNJAB, PAKISTAN, Metro Bus Services, Lahore Pakistan, Third Party Validation of Construction of “Centre of Excellence for Development of Sahiwal & Exotic Br

START Date: 
May, 2012
END Date: 
March, 2014

Countries

·         Pakistan

1.     May 2012 to March 2014:

 

Organization      :               ENGINEERING CONSULTANCY SERVICES PUNJAB

I worked as a SENIOR ENGINEER (Contracts & Construction Management Division) in ENGINEERING CONSULTANCY SERVICES PUNJAB’s Head Office Business and Development Department with some other working experience in this firm is as follows;

1. Project          :               Metro Bus Services, Lahore Pakistan

Designation        :               Site Engineer

Client                  :              Lahore Development Authority, LDA

Contractor           :               MAAKSONS (Private) Limited, Pakistan

Responsibilities

·         Inspection of site works and giving instructions according to check request submitted by the contractor.

·         To inspect different site activities like formwork, steel reinforcement, concreting, asphalt work, earth work, mechanical work (Erection of Steel Girders, Escalators) etc.

·         Making sure the work is being executed according to BOQ.

·         Checking and verifying the IPC submitted by the contractor.

2. Project              :  Top Supervision and Third Party Validation for Different Buildings, Roads and Public Health Projects

Designation       :  Site Engineer

Client                :  City District Government Sheikhupura

     Contractor           :   A Number of Companies

 

Responsibilities

 This project includes evaluation of 31 Roads, 5 Building and 2 Public health projects. Few of these projects were completed and some were in progress.

Following were the responsibilities,

•     Random Inspection of Building and Public Health Projects and submitting Inspection / Observation Notes regarding improvement of different construction activities.

·      Preparation of Monthly Progress Report in line with supervision responsibilities.

·      Monitoring and Verifying the Test Result Reports of different construction materials in accordance with Standard Codes.

·      To ensure that the work has been executed according to Engineers Cost Estimate and Contract Agreement

3.Project : Third Party Validation of Construction of “Centre of Excellence for Development of Sahiwal & Exotic Breed

Designation                        :  Assistant Resident Engineer

Client                                   :  Punjab Livestock and Dairy Development Board

Responsibilities

       The project consists of Steel Sheds, road network and a number of Building units. The project is almost at its completion and the client intends to have a Third Party to evaluate the project. Following were the responsibilities,

·      Visiting site and noting down physical observations regarding construction work for ensuring that the work has been executed according to specifications.

·      Preparation of TPV Report and presenting it to the client.

·      Monitoring and Verification of the Test Result Reports of different construction materials.

·      Sampling of different construction materials and send to laboratory for its necessary testing.

·      Verification of payment record in accordance with Contract Agreement.

Experience Hours (Planning & Scheduling): 
650
Experience Hours (Cost Management): 
1500