Project Co-ordinator /Asstt. Project Manager, Synergy Property Development Services Pvt. Ltd , Pullman Central Park Hotel, Gurgaon,
Synergy Property Development Services Pvt. Ltd
Duration: Aug 2008to Oct 2011
Role: Project Co-ordinator /Asstt. Project Manager
KEY RESULT AREAS;
Client: Central Park Pvt. Ltd., Accor Asia Pacific (India)The worldwide famous European
hospitality group Accor, which operates a total of 4000 hotels worldwide, has decided to
set up a Pullman hotel in Gurgaon. The project will be in collaboration between Accor Asia
Pacific and Central Park developers from India, It will be 5 star hotel having total 285 keys.
Project: Pullman Central Park Hotel, Gurgaon,
Project Area: Aprrox 25024 SQM
Project Cost: 181 Crores
Project Management
- Evaluating project cost / benefits analysis at project decision points.
- Co-ordination, resource allocations and monitoring the project to meet the committed timelines.
- Finalising requirements and specifications in consultation with Client/Operators and Consultant.
- Conducting weekly & monthly project review meetings for evaluating project progress.
- Preparing Project’s Monthly Development Report.
- Preparing agendas & organizing meetings at site & preparing minutes of Site Progress Meetings & Design Team Meetings.
- Creating formats/templates for daily, weekly/monthly progress monitoring.
- Baseline Tracking of Master Schedule.
- Managing Stakeholders (internal and external both).
Planning & Scheduling
- Preparation of Project master & detailed Schedule on the basis of SOW documents with the coordination of different departments.
- Preparing Out to Tender Schedule, Cash Flow, and Drawing Schedule for the Projects.
- Preparing Master Schedule for the project in Primavera & Microsoft Projects.
- Integrate all three schedules (Master schedule, Drawing Schedule and Procurement Schedule).
- Preparing resource loaded schedule in compliance with WBS schedule using “Primavera”.
- Preparing WBS (Work Break Down Structure) and Work Package
- Work & Cost Analysis and Project Budgetary Calculation
- Project Financial Scheduling
- Cost Measuring of Executed Works
- Project Monitoring, Collating and analysing data and preparation of Weekly, Fortnightly and Monthly Reports, Progress S-Curves, Project related presentations and material management.
- Critical Path Analysis (CPA), Total Float Analysis, Variance Trend Analysis and recommendations for recovery.
- Preparation of catch up plans and recovery schedule
- Estimation and forecasting of man power requirement construction scheduling.
- Review, comments and recommendations on contractor’s schedule.
- Interfacing with various disciplines to build up activities sequence and milestones. Equipment, manpower and material loading as per requirement.
- Preparing short term look-ahead reports & Histogram report.
- Scheduling, Planning, Monitoring & Controlling of Construction Activities.
- Scheduling and planning for project, and root cause analysis including budgeting and cost control activities.
- Preparing critical procurement schedules in conjunction with construction programs
- Preparing weekly progress report for client.
- Supervising the progress of the project according to the plan & schedule.
- Estimation and forecasting of man power requirement construction scheduling.
- Weekly planning for Engineering, Construction and Procurement department).
- Preparing 2/3 - week look ahead program
Co-ordination
- Co-ordination with client, architects, consultant and contractors.
- Coordinating the site, technical, drawing related issues with Client, Contractors & multiple consultants (Civil & Services).
- Contractor issues related to drawing.
- Identifying project bottlenecks and undertaking corrective measures.
- Ensuring effective site management and discipline to ensure safe & timely execution of the projects.
- Meeting targeted performance / quality & quantity parameters.
- Identifying areas of obstruction, design constraint / issues and take steps to get job done.
- Involved in Project Planning, Budgeting, Scheduling & Monitoring the physical progress and actual costs.
- Managing Stakeholders (internal and external both).
Supervision & Execution
- Monitoring overall project.
- Updating MIS weekly as well as Monthly basis.
- Ensuring all the construction work is executing as per approved drawing.
- Monitoring the progress of Façade work at construction site.
- Monitoring the progress of Curtain Wall, spider glazing, Glazing Works.
- Monitoring the progress of Canopy work, Skylight works A.C.P work, MS work etc.
- Monitoring the progress of work at construction site.
- Verifying the Re-bar of RCC STRUCTURE at the site.
- Checking finishing work at site.
- Supervising the progress of the project according to the plan &schedule.
- Contractors Monthly RA bill Certification.
Contract Management and Procurement
- Assistance to the Clients in prequalification and engagement of Contractors.
- Understand all design documentations, drawings, specifications, contract terms and conditions.
- Preparing Tender documents for multiple packages for the projects comprising of General/Special terms & conditions of contracts and to vet technical specifications and drawings for the packages.
- Preparing Cost/ Fiscal Aspects/ Technical Comparative of the quotations
- Prepare negotiation strategies & conduct negotiation meetings along with contractors for most appropriate/ budgetary offer for the packages.
- Coordinate technical/ commercial evaluation of vendors with consultants.
- Prepare/ assist in award of work to the tenderer & to conduct kick-off meetings as & when contractor is on board.
- Procurement of site material and coordination with the vendors.
- Supervision/ assistance in preparation & floating tenders to short-listed contractors.