Planning & Project Control Engineer, PT ADHI KARYA, 2 x 7 MW Fired Coal Steam Power Plant Project (PLTU) at Tembilahan, Indragiri Hilir, Riau Province, Sumatra Island, Indonesia
START Date:
September, 2016
END Date:
June, 2017 Sep 2016 – Jun 2017 PT ADHI KARYA (Persero) Tbk.
Assigned as PROJECT CONTROL ENGINEER for 2 x 7 MW Fired Coal Steam Power Plant Project (PLTU) at Tembilahan, Indragiri Hilir, Riau Province, Sumatra Island, Indonesia; Owner: PT. PLN (Persero), Indonesia State Electricity Corporation.
• Developed level 4 schedule for Construction phase by accommodating input from all discipline engineers and use the schedule for weekly monitoring, updating and expediting construction execution.
• Liaised with subcontractors from many disciplines of work to gather and escalate problems at site, discuss and coordinate with discipline engineers to come up with recovery schedule.
• Managed to develop weekly progress report by collecting information from each subcontractor, highlighting significant issue found for Project Management concern.
- Company:
- Industry:
- Job Role:
- Project:
- Region: