MEP Planner, Al moayyed Airconditioning, MKH tower

START Date: 
September, 2009
END Date: 
September, 2013

Employer 1               :           ALMOAYYED AIR CONDITIONING

 

Duration                    :           Dec2012 to Till Now

Position                      :           Planning Engineer

Projects

Ø  MKH TOWER – (B+LG+UG+4P+27 FLOOR+ROOF OFFICE TOWER)

Ø  LUSAIL

Employer 1       

 

Duties & Responsibilities

 

Ø  MEP project  planning of high rise and commercial building and small scale industries using Primavera (P6)

Ø  Prepare MEP baseline program with the help of IFC drawings  along with construction program given by Main contractor.

Ø  Assign required resources for each activities.

Ø  Preparation of  Man power histograms & progress S curve

Ø  Preparation of detailed weekly and monthly progress reports with “S Curve” using MS excel and Primavera project planner.

Ø  Prepare reports and presentations of the project, for monthly progress review meetings.

Ø  Preparation of snapshot activity lists (“1 week look behind”, “2 weeks look ahead schedules” and “3 months look ahead schedules”) for weekly meeting with client.

Ø  Monitoring and comparison of manpower with planned Vs actual to find out productivity.

Ø  Reporting delayed activities to Project Manager & take immediate action to avoid further delay.

Ø  Prepare planned activities & planned manpower details  to all concern Engineers in 1st week of month.

Ø  Monitoring & follow up the drawing schedule & procurement schedule as per planned schedule.

Ø  Prepare delay report of drawing submittals & Material submittals.

Ø  Prepare recovery program to avoid delay

 

 

 

Employer 2               :           BINSAGHAIRY TRADING CO.LLC

 

Duration                    :           March 2011 to Nov 2012

Position                      :           Planning Engineer/ Procurement Engineer

Projects

Ø   Construction of luxury villas

Ø  Residential flats

 

 

Duties & Responsibilities

 

Ø  Preparation of Baseline Schedule with detailed activity listing by referring Construction drawings, in Primavera project planner (P 6 ).

Ø  Preparation of organization chart for the project

Ø  Preparation of histograms &  S curves

Ø  Preparation of detailed weekly and monthly progress reports with “S Curve” using MS excel and Primavera project planner.

Ø  Prepare list of materials  as per site requirements

Ø  Take quotations from suppliers

Ø  Prepare comparison of materials with 3 quotations.

Ø  Negotiate & finalized the price

Ø  Prepare purchase order with delivery time

Ø  Follow up the delivery at site as per LPO date.

Ø   

 

Employer 3               :           AMRITA INSTITUTE OF MEDICAL SCIENCE,KOCHIN

 

Duration                    :           Sep 2009  to Feb 2011

Position                      :           Planning Engineer

Projects                     

Ø  The Point (3B+G+27) Residential & Commercial Building.

 

Duties & Responsibilities

 

Ø  Preparation of detailed weekly and monthly progress reports with “S Curve” using MS excel and Primavera project planner (P 6).

Ø  Drafting of correspondences to client & subcontractors in various matters relating to project.

Ø  Attend progress meetings & presentations with Client, Consultant and discipline heads to monitor progress.

Ø  Prepare reports and presentations of the project, for monthly progress review meetings.

Ø  Preparation of Organization Chart for the project.

Ø  Preparation of target variance reports to analyze progress for critical activities.

Ø  Preparation of snapshot activity lists (“1 week look behind”, “2 weeks look ahead schedules” and “3 months look ahead schedules”) for weekly meeting with client.

Ø  Monitoring and comparison of labor and equipment productivity with company norms.