Planning & Cost Control , Qatar Engineering and Construction Company, Waste Water Disposal Surface facility Project

START Date: 
January, 2011
END Date: 
December, 2011

Planning & Cost Control  for Civil/Piping/E&I/F&G/Telecom works for 2 Off-plot waste water well in Waste Water Disposal Surface facility Project. Client : QATARGAS

  • Prepare Level IV schedule using P6
  • Critical Path identification and risk analysis
  • Resource Loading & obtained “S” Curve
  • Cash flow preparation after “S” curve
  • Resource allocation
  • Sub-contractor finalization & mobilization 
  • Project material Procurement
  • Reporting – Weekly & Monthly
  • Construction (PPC) progress updates and raise invoice
  • Cost reporting and updates
  • Study and analyze the critical activities & list out the hold point and highlighted to client.